A phased interior renovation of an occupied professional office, replacing aging finishes with an open workspace layout, updated conference rooms, and a new break room, completed in stages so staff could continue working throughout construction.
4 mo
Total Duration
3
Construction Phases
0
Business Closures
The Challenge
The client needed to stay open for business throughout construction, which meant no single phase could take more than one wing of the office offline at a time.
Our Approach
We split the renovation into three sequential zones with dedicated temporary workspace for displaced staff, scheduling noisy or disruptive work outside of core business hours where possible.